Quiz Planning-Risk
Test Summary
0 of 10 Questions completed
Questions:
Information
You have already completed the test before. Hence you can not start it again.
Test is loading…
You must sign in or sign up to start the test.
You must first complete the following:
Results
Results
0 of 10 Questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 point(s), (0)
Earned Point(s): 0 of 0, (0)
0 Essay(s) Pending (Possible Point(s): 0)
Average score |
|
Your score |
|
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Current
- Review
- Answered
- Correct
- Incorrect
-
Question 1 of 10
1. Question
As the project manager, you kept all the project documentation on your laptop’s hard disk. You have planned for the worst risk, hard disk crash, so you did a weekly backup on a portable drive that you carried in your laptop bag. One day on your way back from the office, you stopped to buy a cup of coffee. When you returned to your car, you found the window was broken and the laptop bag missing. Both your laptop and portable backup device were lost. You failed to identify theft as a risk. All of the following could have been a response planned for such a risk except:
CorrectIncorrect -
Question 2 of 10
2. Question
A project in a large organization seems to be growing it’s budget and resource needs every day. The project team has planned for every eventuality, exhaustively, and every risk has been identified and a response is planned. As a result, numerous team resources have been identified as risk owners, and risk management activities now take up 30% of the scheduled activities. Which of the following best describes the reason why this situation has occurred?
CorrectIncorrect -
Question 3 of 10
3. Question
Your project involves the procurement of services. Additionally, a recently approved change request has introduced modifications to the project schedule that now place the procured services on the project’s critical path. Your team has informed you that there may be multiple risks that could reduce the likelihood of meeting the milestone established between your company and the vendor. To not negatively impact the total schedule length of the project what action should you take next?
CorrectIncorrect -
Question 4 of 10
4. Question
What is the output of a decision tree analysis?
CorrectIncorrect -
Question 5 of 10
5. Question
Which of the following describes the best possible way to prepare for project risks that cannot be identified prior to the project starting and that can only be recognized after they have occurred?
CorrectIncorrect -
Question 6 of 10
6. Question
What is the best description of sensitivity analysis?
CorrectIncorrect -
Question 7 of 10
7. Question
When the customer is part of the team, which of the following tools and techniques is most valuable while performing probability and impact analysis?
CorrectIncorrect -
Question 8 of 10
8. Question
For a simple yearlong project, when does risk identification happen?
CorrectIncorrect -
Question 9 of 10
9. Question
Which aspect of an organization’s environment can contribute to project risks?
CorrectIncorrect -
Question 10 of 10
10. Question
You are the project manager of a technology project and are currently completing a risk identification exercise. Which of the following best defines what the Identify Risks process actually identifies?
CorrectIncorrect