Quiz Monitoring-Stakeholder
Test Summary
0 of 10 Questions completed
Questions:
Information
You have already completed the test before. Hence you can not start it again.
Test is loading…
You must sign in or sign up to start the test.
You must first complete the following:
Results
Results
0 of 10 Questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 point(s), (0)
Earned Point(s): 0 of 0, (0)
0 Essay(s) Pending (Possible Point(s): 0)
Average score |
|
Your score |
|
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Current
- Review
- Answered
- Correct
- Incorrect
-
Question 1 of 10
1. Question
Which Monitoring and Controlling process is focused on adapting and improving the engagement activities as a project progresses?
CorrectIncorrect -
Question 2 of 10
2. Question
Which of the following data analysis techniques used during the Monitor Stakeholder Engagement process helps to determine the engagement position of stakeholder groups and individuals?
CorrectIncorrect -
Question 3 of 10
3. Question
Which of the following is an input to the Monitor Stakeholder Engagement process?
CorrectIncorrect -
Question 4 of 10
4. Question
Your project has completed half of its deliverables and is in the middle of the executing process group. You created a stakeholder register during the initiating process group which was then used to create a stakeholder management strategy. During the Monitor Stakeholder process, you become aware of a highly influential stakeholder that has not been identified in the stakeholder register. What is the best course of action?
CorrectIncorrect -
Question 5 of 10
5. Question
The stakeholder engagement plan is updated in all of the following situations, except:
CorrectIncorrect -
Question 6 of 10
6. Question
Seeing the declining support ratings for your project from the banks that finance your project, your sponsor, in a state of panic, asks you to take action to build positive support. Which of the following best describes what you would do next?
CorrectIncorrect -
Question 7 of 10
7. Question
What is the Controlling process in the Project Stakeholder Management knowledge area?
CorrectIncorrect -
Question 8 of 10
8. Question
Through data analysis during the Monitor Stakeholder Engagement process, your team has identified a key stakeholder with a low level of engagement. Additionally, the team has proposed a corrective action that if implemented will help to increase the engagement level of the stakeholder in question. What is the most appropriate action to take?
CorrectIncorrect -
Question 9 of 10
9. Question
The ability of the project manager to correctly identify and engage all __________ in an appropriate way can mean the difference between project success and failure.
CorrectIncorrect -
Question 10 of 10
10. Question
Your team has identified that a key stakeholder has an engagement level below the desired level defined in the stakeholder engagement assessment matrix. The team is unsure of the reasons why the stakeholder engagement plan established is not having the desired impact. Which data analysis technique would you suggest that the team use in this situation?
CorrectIncorrect