Quiz Planning-Quality
Test Summary
0 of 10 Questions completed
Questions:
Information
You have already completed the test before. Hence you can not start it again.
Test is loading…
You must sign in or sign up to start the test.
You must first complete the following:
Results
Results
0 of 10 Questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 point(s), (0)
Earned Point(s): 0 of 0, (0)
0 Essay(s) Pending (Possible Point(s): 0)
Average score |
|
Your score |
|
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Current
- Review
- Answered
- Correct
- Incorrect
-
Question 1 of 10
1. Question
A project is underway to build a road which makes use of tar and gravel. Road leveling machines are used after the materials have been laid. Which of the following techniques is best suited to represent the order in which work has to be done?
CorrectIncorrect -
Question 2 of 10
2. Question
Nelson is a project manager who is planning the quality management processes and activities. He decided to make use of a matrix diagram to assist his current efforts. Which of the following is the most likely activity that Nelson is performing?
CorrectIncorrect -
Question 3 of 10
3. Question
What would be the best way to develop a quality management plan for a product development project that is taking a totally new approach to product development, unprecedented in the industry?
CorrectIncorrect -
Question 4 of 10
4. Question
You are the project manager of a software development project. The code written by the programmers was tested by the quality auditors. Some of the work was found to have significant logical errors that required a complete rewrite. The cost of redoing the work can also be called which of the following?
CorrectIncorrect -
Question 5 of 10
5. Question
Which of the following is not a characteristic of the cost of nonconformance?
CorrectIncorrect -
Question 6 of 10
6. Question
Which individual is responsible for the quality of the project deliverables for a building construction project?
CorrectIncorrect -
Question 7 of 10
7. Question
A project manager was informed by a team member that the internal failure cost is very high. Which of the following is an example of internal failure costs that the team member may be referring to?
CorrectIncorrect -
Question 8 of 10
8. Question
A project manager on a software development project wants to use the quality management plan from his previous similar project, which was very successful. What would you advise him?
CorrectIncorrect -
Question 9 of 10
9. Question
During a negotiation with a customer regarding the work to be performed and the effort involved across the entire project, the customer objects to the effort being proposed to complete the quality control and quality management activities. As the project manager, which one of the following concepts should you use to explain the value that the proposed quality control and management activities will have to the project?
CorrectIncorrect -
Question 10 of 10
10. Question
How does quality relate to the project scope?
CorrectIncorrect